Capacity Recovery

Recover the capacity your service already has.

A service is sized for the current it carries at its busiest moment, and part of that current often does no useful work. We find where it goes, design the changes that return it, run the control on site, and measure the panel again to show what came back.

Engineering reportPage 1 of 12

Specimen: Panel A, Measured Again

Worked example, before and after
Peak before
556 kVA
Peak after
470 kVA
At the measured peak

86 kVA back on the service, and the new load fits.

Reviewed and signed by a licensed engineer under their own licenceSpecimen

Where the Capacity Goes

Cables, breakers and transformers are rated for current and the heat it produces. The limit that matters is the current a facility draws at its busiest moment, and that current has three parts. Only the first is doing the work the facility exists for.

Over the ratingIt fitsThe service ratingBefore recoveryAfter recoveryUSEFUL LOADPOWER SPENT ON NOTHINGCURRENT THAT DOES NO WORKTHE LOAD YOU WANT TO ADD
Useful load
Refrigeration holding temperature, cooling in occupied rooms and kitchens during service. This is the floor of what the service must carry. When it exceeds the rating on its own, the upgrade is needed and the study says so.
Power spent on nothing
Real power drawn when its purpose is absent. It shows on the energy bill, and it occupies capacity when it runs at the moment of peak demand.
Current that does no work
Current that heats cables and transformers while delivering almost no energy. It comes from motors, from the electronics in drives and chargers, and from phases loaded unevenly. An energy bill barely shows it, and an ammeter does.

Power Spent on Nothing

Commercial equipment often keeps running when nobody needs it. The share that occupies capacity is the share still running at the peak, and it comes from five sources.

50%50%100%100%If power followed airflowActual fan power80% of the airflow, 51% of the powerAIRFLOW, AS A SHARE OF FULL SPEEDFAN POWER

The affinity laws for fans and pumps, ASHRAE Handbook. Power scales with the cube of flow, so 80% of full airflow needs 0.8 × 0.8 × 0.8, or 51%, of full power.

Loads that start together
Rooftop units stage at the same moment, defrost cycles share a schedule, and kitchen preheat lands on the morning cooling ramp. The peak is set by what coincides, so staggering the same equipment lowers it.
Fans and pumps at full speed
Fan and pump power rises with the cube of flow. A fan held at full speed for a partial need draws far more than the need requires, and slowing it by a fifth removes about half of its power.
Systems working against each other
Heating and cooling in the same space, exhaust drawing out air that was just conditioned, and anti-sweat heaters at full duty in dry weather.
Setpoints beyond the requirement
Rooms cooled below comfort, storage colder than its specification, and compressed air above the pressure the tools need. Every step past the requirement is drawn continuously.
Equipment that has degraded
Fouled condensers, loaded filters and failed economizers make equipment draw more than its rated input for the same duty.

Current That Does No Work

This part of the current delivers almost no energy, so an energy audit rarely finds it. It still occupies the rating, because a service carries amperes whether or not they do any work.

456 kW of work, in both cases318 KVAR AT 0.82114 KVAR AT 0.97Power factor 0.82: 556 kVAPower factor 0.97: 470 kVA86 kVA returned to the serviceAPPARENT POWER THE SERVICE CARRIES

A worked calculation, apparent power equals real power divided by power factor. It describes no particular facility. Capacitor application follows IEEE Std 1036.

Reactive current

Motors and transformers draw current that lags the voltage and hands its energy back every cycle. The service carries it all the same. A facility drawing 456 kW at a power factor of 0.82 presents 556 kVA to its service. Corrected to 0.97, the same 456 kW presents 470 kVA, and 86 kVA of the rating comes back with no change to the work being done.

Because correction saves almost no energy, efficiency programs seldom pursue it. On a service that is short of capacity, it is one of the most direct changes there is.

ABCABCThe limit of each phaseLoaded unevenlyRebalanced

Unbalanced phases

A three-phase service is full when its busiest phase is full. Single-phase circuits landed unevenly leave room on two phases while the third reaches its limit. Moving circuits between phases needs no new equipment and returns the gap between the heaviest phase and the average. Unbalanced voltage also derates three-phase motors, as NEMA MG 1 describes.

What You Receive

  1. Determination

    A high-level estimate of the capacity your service has, with nothing fitted to the panel.

    An estimate
  2. Investigation

    The detailed analysis of your demand, and the kW that can be unlocked.

    The detailed analysis
  3. Intervention

    Which loads can change at the peak, and how many kW each change frees, identified on your own measured demand.

    Identified load by load
  4. Managed Capacity

    The control runs on a controller Wattif keeps running on site, and the panel is measured again.

    Signed by a licensed engineer

Managed Capacity is charged per kW of capacity returned, measured on your panel, and quoted for your site before any work starts.

When Recovery Is Not Enough

None of the sources on this page can be assumed for a given facility. A well-run site may carry no wasted power and still draw more current than its work needs, while a site with a sound power factor may run its exhaust fans all night. The first task of the investigation is to find out which facility it is looking at.

When the useful load on its own exceeds the service rating, no recovery is enough. The investigation says so, and the upgrade is then designed against a measured basis.

An upgrade may still be the right answer. The decision to make one should follow a measurement.

Holding an upgrade quote? Measure the panel before you commit to it.

Start with the Capacity Determination Report
Capacity Recovery | Wattif