Electrification

Most facilities have more room than their drawings say.

A service is sized by what a facility could draw, and a year of its own record says what it does draw. We measure the room you have, free the current the peak is wasting, and hold the new load inside the limit, so the chargers, the heat pumps or the new tenant go in on the service you already have.

DeterminationSpecimen

Capacity Determination Report, Main Service

12 months of utility interval data
Existing, measured
220 A
With the new load
360 A
Verdict

Fits, with 40 A to spare on a 400 A service.

Reviewed and signed by a licensed engineer under their own licence

Two Ways to Add Load

When a facility wants to add load, the utility offers one route and the panel holds another.

WITHOUT A MEASUREMENTThe project waits on a service upgrade nobody has checked the need forWITH ONEMeasured in daysThe project proceeds, or the upgrade starts with evidence instead of an argumentTHE ANSWERWHERE THE OTHER ROUTE GETS TO ITS ANSWER

A shape, and it describes no particular facility or utility.

The upgrade, or the measurement

A service upgrade adds supply. It is designed against what the facility could draw, it takes the utility's time, and the facility pays for every ampere of it whether or not the peak ever gets there.

The other route reads what the facility does draw. A year of 15-minute demand shows the real peak, the code allows the new load to be added to that, and where the answer is still tight, the current at the peak that does no useful work can be returned and the new load held under a limit.

Most facilities find room on the second route. The ones that do not get a signed study to size the upgrade against, which is still faster than guessing.

What Decides Whether It Fits

The year's highest demand

The existing load is the busiest 15 minutes the service carried in 12 months, read from the utility's record or, where there is none, from 30 days on the panel.

What you are adding, as the code counts it

The new load is counted under the code's own rules for that equipment: at its full rating, or under the limit a listed load management system holds it to.

What can come off the peak

Loads that run together and need not, equipment drawing above its duty, phases out of balance. Each is current at the peak that can be returned before any upgrade is sized.

What We Answer

How We Do It

  1. Utility account connected12 months of 15-minute demand, with the tariffHighest demand each month, in amps0100200300JFMAMJJASOND400 A ratingFirst answerHarlow Street MotorsMeasured peak220 ARating400 AWith the chargers360 AVerdictFitsFrom the utility's own record.01 Utility data

    We read 12 months of your utility's interval data first, with no visit, and that gives a first answer.

  2. MAIN 400 ASchedulePanel MDPHarlow Street Motors400 A, 208Y/120 VCKTSERVESBREAKER1Rooftop unit 150 A2Rooftop unit 250 A3Showroom lighting60 A4Lot lighting30 A5Service bay lifts60 A6Air compressor40 A7Offices, parts room100 A8Water heater40 A9Car wash bay40 A10Fire alarm, egress20 A02 Panel record

    We write the panel down circuit by circuit. Sensors go on only where the utility data cannot settle it.

  3. 360 AExisting load plus the chargersMeasured peak220 ACode margin+55 A4 chargers+85 A40 A to spare400 AratingFits03 Calculation

    We add the new load to the measured peak with the margin your code requires, and set the total against your rating.

  4. DETERMINATIONThe service supportsthe chargers.Existing, measured220 AWith the code's margin275 AChargers+85 AHeadroom after40 ASigned by a licensed engineerHarlow Street MotorsE-000CALCULATION1 Maximum demand, 12 months220 A2 Line 1 with the code margin275 A3 4 EV chargers+85 A4 Total, line 2 + line 3360 A5 Service rating400 A6 Spare, line 5 less line 440 AHarlow Street MotorsE-301SINGLE-LINE400 A mainEV, newExisting feedersHarlow Street MotorsE-101PANEL SCHEDULE1Rooftop unit 150 A2Rooftop unit 250 A3Showroom lighting60 A4Lot lighting30 A5Service bay lifts60 A6Air compressor40 A7Offices, parts room100 A11EV chargers, proposedHarlow Street MotorsE-201BASISDemand recordUtility dataMain breaker 400 AField photoRooftop unit nameplatesField photoCar wash bay loadStated by ownerTransformer impedanceUnverifiedHarlow Street MotorsE-401CERTIFICATIONLICENSEDENGINEERSpecimenSignatureDateLicence expiryHarlow Street MotorsE-00104 Review

    A licensed engineer reviews the calculation and signs it under their own licence.

Watch a determination being made →

What You Are Adding

Chargers
Runs
Counted
00:0006:0012:0018:0024:00400 A service440 A counted, with the new load
The facility today80 A of new load
440 A40 A over the 400 A service

After recovery, 375 A. It fits.

A shopping mall with a customer car park

A 400 A service, chargers wanted in the car park, and a first quote for a service upgrade. Size the chargers and choose when they run: the verdict is the recorded peak counted at the code's margin, plus the new load, against the rating.

Each load we make room for has its own page and its own rule for how it is counted.

What We Measure

12 months of interval data

Your utility's record of demand every 15 minutes, read with your authorisation. It settles most capacity questions with nothing fitted to the panel.

30 days on the panel

Where the utility cannot see the panel in question, a sub-panel or a feeder, loggers go on the board for 30 days and record every 15 minutes, the interval your demand is billed on.

The panel, circuit by circuit

The breaker list typed from photographs of the board, so every reading has a circuit name and a rating beside it, and the calculation stands on a verified record.

Loggers are fitted and collected by a licensed electrician with the panel live, and they come off at the end of the window. The install is checked on the visit, because a logger only reads back at the end.

Who Asks for It

  • Car showroomCustomer charging
  • Fleet depotOvernight charging
  • ApartmentsChargers for residents
  • OfficeHeat pumps
  • RestaurantInduction and extract
  • WarehouseForklifts and docks
  • SchoolElectric kitchens and heat
  • Transit depotBus charging

What You Receive

  1. The verdict

    Fits, tight or short, with the measured peak and the rating behind it.

    In every report
  2. What frees capacity

    The current at the peak that does no useful work, circuit by circuit, and the change that returns each part.

    Where the answer is tight or short
  3. The peak, measured again

    The service read again with the changes made and the new load running, signed on the measured number.

    After the changes

What It Needs

Electrification starts from 12 months of your utility's interval data, or 30 days on the panel where the utility cannot see it. Nothing is fitted for the first answer.

Wattif performs no electrical work. Any change to the facility is made by a licensed electrician, and the controller that holds the new load inside the limit is ours, run by us.

Adding load? Check the service before you price the upgrade.