Free Load Analysis Tools · NEC 220.87 · 120.87 in the 2026 Code

Headroom Check: For When the Load Calc Says No.

The Article 220 calculation runs high on older buildings by design. Before you quote a service upgrade, run the recorded-data math: enter the service, the real peak, and what you are adding. Free, no sign-up, printable.

SITE & PROPOSED LOADSINPUTS

On this service

Either one takes the 30-day recording off the table, because the meter reads net rather than load.

Proposed added loads

Amps are computed from kW at the selected system voltage. Three-phase: kW × 1000 ÷ (1.732 × V). Enter nameplate kW. Anything ticked cont. is counted at 125 percent, which is how Article 220 treats a load running three hours or more.

220.87 HEADROOM CHECKAug 25, 2026
Site800 A · 480Y/277 V · 3Φ
Peak demand × 125%515 A
Proposed loads, continuous at 125%+ 69 A (46 kW)
Projected total vs rating584 A of 800 A
Existing at 125%Proposed
HEADROOM: 216 A

Looks like it clears, on an estimate, which proves nothing to a plan reviewer. 220.87 requires a year of demand data or a 30-day recording. The load study is that proof.

Borderline or Over? A Recording Settles It.

The kit ships to your shop, clamps on in 15 minutes, records for 30 days, and the submittal-ready report carries your brand.